AN ANALYSIS CAUSES OF LINE DISTURBANCE IN ELECTRICITY DISTRIBUTION IN PT. PLN (PERSERO), ULP EAST BINJAI

  • Eky Firdian Fauzi Program Study Electrical Engineering, Faculty of Science and Technology Universitas Pembangunan Panca Budi Medan
  • Siti Anisah Program Study Electrical Engineering, Faculty of Science and Technology Universitas Pembangunan Panca Budi Medan
  • Hamdani Hamdani Program Study Electrical Engineering, Faculty of Science and Technology Universitas Pembangunan Panca Budi Medan
Keywords: Causes of Disturbance, Distribution Lines, Fault Trees

Abstract

The distribution line is the section of the electricity line that is closest to the community; it is divided into two parts: primary and secondary distribution lines. PLN primary distribution voltages are 20 KV, 12 KV, and 6 KV. The primary distribution voltage that PLN typically produces is 20 kV. The purpose of this study is to use FTA to determine the main causes of disturbances in the electricity distribution line at ULP Binjai Timur (Fault Tree Analysis). The large difference between the electrical energy sent from the substation and the electrical energy obtained from customer consumption demonstrates the study's findings. The following are the causes of these disturbances: component JTM (I1) with as many as 55 faults (12.5 percent), JTM equipment (I2) with as many as 30 faults (6.7 percent), transformer faults (I3) with as many as 8 faults (1.8 percent), natural disturbances (I4) as many as 1 disturbance (0.2 percent), external disturbances (E1) as many as 15 disturbances (3 percent), natural disasters (E2) as many as 61 disturbances (13.7 percent), the work of other parties/animals (58.2 percent). After conducting research on the causes of disturbances in the electricity distribution line at ULP Binjai Timur and analyzing the data with Fault Tree Analysis (FTA), it was discovered that the main cause of disturbance is a human disturbance, manifested as kites, banners, and digging PDAM channels

Downloads

Download data is not yet available.

References

[1]. A. Spabla and Hadi Abdul, Ir. 1986. Sistem Distribusi Daya Listrik.. Jakarta
[2]. Weedy, BM, 1978 Sistem Tenaga Listrik, edisi ketiga, penerbit aksara persada Indonesia
[3]. Arismunandar, A, (1979), Teknik Tenaga Listrik, Jilid II Cetakan kelima, penerbit PT. Pradnya Paramita, Jakarta
[4]. Arsip and Dookumentasi PT. PLN (Persero) wilayah SULSELTRABAR Area Makassar Rayon East Makassar BM Weedy, "Sistem Tenaga Listrikā€
[5]. Aryza, S. (2018). a Novelty of Quality Fertilizer Dryer Based on Solar Cell and Ann.
[6]. Anonym, 2017.Jaringan Distribusi. http://www.duniapembangkitlistrik.blogspot.com/.Line-distribution-electricity. accessed on 6th September 2017
[7]. Aryza, S., Irwanto, M., Lubis, Z., Siahaan, A. P. U., Rahim, R., & Furqan, M. (2018). A Novelty Design Of Minimization Of Electrical Losses In A Vector Controlled Induction Machine Drive. In IOP Conference Series: Materials Science and Engineering (Vol. 300, No. 1, p. 012067). IOP Publishing.
[8]. HarSuhardi, bandung t, Teknik Distribusi Tenaga Listrik jilid I, direktorat pembinaan sekolah menegah kejuruan. Depdiknas, 2008
Published